A workstream reports green based on completed tasks, but integration is blocked. What status would you report?

Instruction: Write a corrected status with evidence, owner and next checkpoint. Separate progress from readiness.

Context:

Fictional workstream: eight of ten tasks are complete. The two incomplete tasks are API authentication and production-like integration testing; the dependent team cannot begin its acceptance test without them. Acceptance is due in three working days. The authentication owner estimates two days; integration needs two days afterward. No approved workaround exists.

Updated

Official answer available

Read the opening below, then unlock the full answer and practical guidance.

“At risk: eight of ten tasks are complete, but the dependency required for acceptance is not ready. Authentication needs two days, followed by two days of integration, against a three-day deadline. Current sequence misses the needed handoff by one day...