[Planning] All 20 UAT scenarios have run, but two critical scenarios failed. Can you mark the milestone complete?
Instruction: Eighteen scenarios passed and the other two failed. The milestone was defined as all 20 scenarios passed with no unresolved critical defects. Explain the status, decision evidence and next steps without changing the agreed criteria silently.
Updated
Official answer available
Read the opening below, then unlock the full answer and practical guidance.
I would report that test execution is complete, but the agreed milestone is not. Eighteen of 20 scenarios passed, so the scenario pass rate is 90%; the two critical failures also violate the stated no-unresolved-critical-defect criterion. A high aggregate percentage does not override that condition.
I would confirm the failure evidence and affected workflows with the test and delivery leads, record severity and...