A major customer requests an off-roadmap feature that competes with a portfolio commitment. What would you recommend?

Instruction: Use the supplied evidence to make a capacity recommendation, distinguish opportunity from committed revenue and explain the customer response.

Context:

Fictional quarter: engineering has 12 person-weeks remaining. A contractual security commitment needs four and cannot be deferred; an onboarding improvement supported by eight customer interviews needs six. One customer representing $120,000 annual recurring revenue asks for a bespoke export estimated at five person-weeks. Their renewal is in 60 days, but they have not said the feature is a condition. An approved existing export plus a one-person-week support setup might meet their underlying need; that must be tested with them. Product leadership owns roadmap changes.

Updated

Official answer available

Read the opening below, then unlock the full answer and practical guidance.

The three full initiatives require 4 + 6 + 5 = 15 person-weeks, exceeding the remaining 12 by three. I would protect the four-week contractual commitment and validate the one-week supported-export option with the customer before displacing the six-week onboarding work. That combination uses 11 weeks if the alternative meets the need.

The $120,000 account...