[Communication] Three teams confirm plan version 3, but the fourth still uses version 2. How do you close the loop?
Instruction: An authorized decision changed a handoff date in plan version 3. Three of four teams confirmed the change; the fourth team still has version 2 in its working schedule. Explain what you would verify, update and communicate before declaring the decision implemented.
Updated
Official answer available
Read the opening below, then unlock the full answer and practical guidance.
I would report that the communication loop is still open. Three of four confirmations is 75% acknowledgement coverage, but even that does not prove the updated handoff is implemented. The fourth team's working schedule contains a known contradiction.
I would verify the authorized decision and its effective date, then contact the fourth team's lead to understand whether the issue is a missed message, an outdated link or...