[Execution] Eighty of 100 tasks are closed, but none of three required workflows is verified. How would you report progress?
Instruction: Task sizes vary. Three end-to-end workflows are required for acceptance; none has been verified, and an external integration date is unconfirmed. Explain what the task count establishes, what remains unknown and what you would do next.
Context: Assesses whether the candidate distinguishes activity counts from accepted capability and remaining schedule risk, instead of equating closed tasks with percent of delivery completed.
Updated
Official answer available
Read the opening below, then unlock the full answer and practical guidance.
I would report that 80 of 100 tracked tasks are closed, which is an 80% task-closure rate. I would not call the project 80% delivered: the tasks have different sizes and dependencies, and closure counts do not establish effort completed, customer value or readiness...