[Planning] How do you re-baseline a project while preserving accountability for the original plan?
Instruction: Explain how you would re-baseline a project when the original plan no longer reflects delivery reality.
Context: Assesses whether the candidate can reset a project plan honestly while maintaining confidence and control.
Updated
Official answer available
Read the opening below, then unlock the full answer and practical guidance.
I would re-baseline when an approved plan no longer provides a useful control reference, not to hide a missed commitment. First I would establish what changed: scope, assumptions, dependencies, resources or execution performance. I would show the variance from the previous baseline and acknowledge planning or delivery mistakes where the evidence supports them.
Then I would work with delivery owners to...