[Stakeholders] How do you know when a stakeholder concern is valid risk versus normal delivery discomfort?

Instruction: Explain how you tell the difference between a concern that truly threatens delivery and one that reflects normal tension around project change.

Context: Assesses whether the candidate can evaluate stakeholder concerns with judgment instead of reacting to every worry equally.

Official answer available

Preview the opening of the answer, then unlock the full walkthrough.

I usually test that by looking at impact, evidence, and repeatability. Does the concern point to something that could materially affect scope, timeline, readiness, adoption, or confidence? Is there evidence behind it, or is it more of a general discomfort with change or uncertainty? And is the pattern isolated, or does it keep showing up across...