[Stakeholders] How do you handle a stakeholder who bypasses the project process and goes directly to the team?

Instruction: Explain how you would respond when a stakeholder starts sending requests or direction directly to the team outside the agreed path.

Context: Assesses whether the candidate can protect project control without overreacting to informal end-runs.

Official answer available

Preview the opening of the answer, then unlock the full walkthrough.

I would address it quickly, because if that pattern continues, the project loses one of the most important things it has: a shared way of making and communicating changes. I would first understand what is happening and whether the stakeholder is bypassing the process because it feels too slow, too unclear, or simply inconvenient.

Then I would...