A confirmed vendor delay threatens a committed milestone. How would you present recovery options to the executive?

Instruction: Compare the stated recovery options and give a recommendation with the decision deadline, cost and quality constraints.

Context:

Fictional project: there are ten working days before the promised launch. A vendor now confirms delivery in six working days; integration and validation require five more days after delivery. An approved alternative can arrive in three working days but adds $12,000 and still needs five days of integration and validation. Scope cannot remove the required validation. The sponsor approves additional spend and customer date changes.

Updated

Official answer available

Read the opening below, then unlock the full answer and practical guidance.

The current path needs 6 + 5 = 11 working days, missing the remaining ten-day window by one day under these assumptions. The approved alternative needs 3 + 5 = 8 days and costs an extra $12,000, leaving two days before the promised date...