Leadership wants all planned features by a fixed date, but capacity is insufficient. How would you negotiate scope?

Instruction: Calculate the capacity gap and propose a feasible option without promising unverified productivity gains.

Context:

Fictional two-week delivery window: the team has 40 engineer-days available after support and testing allocations. Required security work is 10 engineer-days; core workflow is 20; optional reporting is 18. These estimates already include review and are not parallelization promises. Security and core workflow are mandatory for launch. The sponsor owns scope; engineering validates feasibility.

Updated

Official answer available

Read the opening below, then unlock the full answer and practical guidance.

The full request is 48 engineer-days against 40, an eight-day capacity gap. The required security and core workflow total 30, leaving ten engineer-days of stated capacity...