A plan schedules dependent tasks in parallel. How would you produce a feasible delivery sequence?
Instruction: Calculate the earliest finish from the supplied durations and dependencies. Explain the resource constraint and the next planning checks.
Fictional plan: requirements take two working days. Only afterward can build A (four days) and build B (three days) start. The same engineer must perform both builds and cannot split days. Integration testing takes two days after both builds finish; a tester is available then. Work starts at the beginning of day 1; no holidays or external wait times are assumed. Leadership's draft shows completion at the end of day 8.
Updated
Official answer available
Read the opening below, then unlock the full answer and practical guidance.
Requirements occupy days 1–2. With one engineer, the two builds take seven nonoverlapping days: A on days 3–6 and B on days 7–9, or the reverse order. Integration testing runs days 10–11...